JETBRIDGE AND BAGGAGE LIFT INSTALLATION
DULUTH INTERNATIONAL AIRPORT
DULUTH, MN
Completed:  February 2005

A 30 year old Jetway System was replaced with a new Jetbridge Technologies System.  The old jetbridge was removed and disposed of under the contract.  After installation, the air carrier requested that the jetbridge by outfitted with a baggage lift system.  Upon arrival, the lift system required extensive modifications performed on site by HMI prior to the install.  HMI completed 100% of the work under tight security regulations and without disruption to the terminal's air carrier operations.



AIR TRAFFIC CONTROL TOWER GROUNDING CABLE UPGRADE
DULUTH INTERNATIONAL AIRPORT
DULUTH, MN
Completed:  November 2003

The Air Traffic Control Tower was constructed in the early 1950's.  The electrical grounding system within and surrounding the building was in poor shape at best requiring repair and replacement.  Under an FAA contract, HMI removed the concrete around the building and installed the new cable and grounding rods.  New ground plates were also installed inside the building.  The project was completed 100% by HMI, on time, on budget, and without disruptions to ATC operations.
MISCELLANEOUS
Copyright © 2011 HMI. All Rights Reserved.
PROJECTS
PROJECTS
HOME      PROJECTS      JOB SITES      ABOUT      CONTACTS      SPONSOR
PROJECTS